The Second Biggest Petroleum Producer and Leading Operator in Viet Nam

News2014-01-07 16:50:45

2013 - A continuing success

2013 Ca Ngu Vang Field (CNV) and Te Giac Trang Field (TGT) Production Targets were achieved on 28th October and 6th December 2013 respectively.

By the end of the year, TGT Field Production achieved  107% of its target for both Crude Oil and Associated Gas.  In addition CNV Field achieved 120% of its target for Crude Oil Production and 139% of its target for Associated Gas Production.

During the  year, all TGT and CNV operations were absolutely safe with a total of 936,674 man hours worked without lost time injuries.