The Second Biggest Petroleum Producer and Leading Operator in Viet Nam

E&P Activities2011-12-21 21:52:08

Production - Hoang Long

TGT Field Development

The TGT Field development scheme involves the phasing of production of the reserves from the different Fault block accumulations with 12 months between First Oil from the H1-WHP and First Oil from the H4-WHP.

Crude oil from the TGT Field is transported via a subsea pipeline system to the FPSO Armada TGT 1 which has a processing capacity of 55,000 barrels of oil per day (BOPD) then it is processed, stored and exported to regional oil refineries. Gas will be transported through a pipeline to the near-by Bach Ho Facilities for processing and transportation to shore via the existing infrastructure for further distribution to meet domestic demand. The TGT Field Oil output is expected to be between 40,000 and 55,000 BOPD and gas production is approximately 30 million cubic feet per day.

HLJOC continues fabricating Platform Topsides in preparation for H4-WHP First Oil which is targeted for mid-2012. The facilities were designed to accommodate the potential future tie-back of surrounding discoveries in the area.

 

Full Field Te Giac Trang Facilities Development Scheme